FACILITIES ROOF

STATUS
Bidding

BUDGET
$550,000

ARCHITECT
HGHB Architects

GENERAL CONTRACTOR
Pueblo Construction

PROJECT DESCRIPTION

Replace facilities roof with combination of standing seam metal roof at public facing areas and composition shingle in back of house areas. Replace three rooftop package HVAC units.

PROJECT SCHEDULE

Design: October 2021
DSA Review: June 2022 - August 2022
Bidding: September 2022
Construction: May 2023 - August 2023
Close Out: June 2023